Page 85 - 2016 TGI CSR 電子書
P. 85
Item CO 2
Energy conservation Energy Amount reduced Photo
measures conserved conserved
Factory (ton)
Replaced the emergency Electricity 370 0.20
exit lights. (KWH)
Added front and back Electricity
door switch to the boiler (KWH) 54,892 28.98
to conserve energy.
Taichung
Factory Alternative plan for the
dehumidifiers in the Electricity 28,990 15.31
lamination cleanroom on (KWH)
off days.
Other energy saving Electricity 5,677 3
measures. (KWH)
Switch to LED light bulbs Electricity 37,843 19.98
across the factory. (KWH)
Energy conservation Electricity
for HVAC in fabric (KWH) 113,005 59.67
examination.
Lukang
Factory
Switch to LED light bulbs Electricity
14,668 7.76
in street lights. (KWH)
Use the high pressure Electricity
pump VFD to control the (KWH) 5,280 2.79
RO water output.
Two 150hp circulating
water pumps are
Changpin shut down during the Electricity 80,640 42.6
Factory maintenance (60 hours (KWH) 83
each month for the
coating line).